Correction to ASX Announcement
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
20 January 2026
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3, 28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Correction to ASX Announcement
TG Metals Limited (ASX: TG6) (“Company”) refers to the announcement released on 20 January 2026
titled ‘New Gold Discovery 550m South and Along Strike of Existing Van Uden Mineral Resource’
(“Announcement”).
The Announcement referenced a drilling intercept of “11m @ 1.19 g/t Au from 65m”. The correct
intercept is “11m @ 1.90 g/t Au from 65m”.
The Announcement has been re-released in a corrected form and is attached.
This release has been authorised by TG Metals Board of Directors.
ASX ANNOUNCEMENT
RELEASED 20 JANUARY 2026
New Gold Discovery 550m South and Along Strike of
Existing Van Uden Mineral Resource
Highlights
TG Metals Limited (TG Metals or the Company) (ASX:TG6) is pleased to provide results from
exploration drilling at the Van Uden Gold Project (Van Uden or the Project). The drill holes
were targeting gold in soil anomalies announced 9 September 2025.
These results are from reverse circulation (RC) drillholes south of the currently defined Van
Uden gold deposit (Figure 1). Multiple gold zones were intercepted in similar geological
positions to the MRE1 to the north. This extends the strike of the Van Uden Deposit by more
than 550 metres to over 3 km, within an overall mineralised strike defined by drilling and
surface geochemistry of more than 7 km, yet to be fully tested with drilling.
New results highlights include:
• TGGR124: 3m @ 3.46 g/t Au from 71.0m, including 1m @ 9.83 g/t Au from 71.0m
• TGGR127: 11m @ 1.90 g/t Au from 65.0m (including 1m @ 6.18 g/t Au from 65m
and 1m @ 9.66 g/t Au from 74m) and 3m @ 0.90 g/t Au from 44.0m and 5m @
0.31g/t from 35m
1. MRE - See Table A
■ High grade assays confirm a new gold discovery circa 550m to the south
and along strike of the existing Van Uden Mineral Resource1
■ Excellent first pass shallow, gold results, including:
■ 3m @ 3.46 g/t Au from 71m
■ 11m @ 1.90 g/t Au from 65m
■ These step out holes extend the defined gold deposit to more than 3 kms
and could materially add to the existing resource
■ Overall mineralised strike defined by drilling and surface geochemistry is
over 7kms, showing the large-scale gold footprint at Van Uden
■ Results for additional holes testing extensions circa 2.7 km to the south
of these new hits are pending
■ In total, assays are still pending for a further 76 holes, with drilling
expected to recommence at the Project in the next 2 weeks to continue to
extend the mineralisation at Van Uden
ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
2
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
TG Metals CEO, Mr. David Selfe stated;
“This step out drilling program to the south of the Van Uden MRE1 has resulted in a new
discovery of significant widths and grades of gold mineralisation in proximity to the Van Uden
shear. This extends the drill defined gold deposit to more than 3 kms and provide the potential
to materially add to the current resource. The Van Uden shear is proving to be a fertile conduit
for gold mineralisation, initially highlighted by the gold in soil anomalies defined in 2025 and
now confirmed by very positive drill results. Getting economic widths and grades first up is very
encouraging as is the inclusion of high grades above 6 g/t Au in the drillhole intercepts.
There is an additional 2.7 km of Van Uden shear contained within Mining Leases to the south
of the Van Uden MRE, yet to be fully tested with drilling. We still have a lot of drilling assays
pending and each return of data is increasing our confidence of growing the Van Uden deposit.
Further drilling will recommence later this month including our first diamond core drilling. We
look forward to reporting further drill results as they come to hand.”
Van Uden Exploration Drilling
The purpose of this drilling was to test gold in soil anomalies and projected continuations under
shallow cover, along strike of the known Van Uden gold deposit. Drilling positions were limited
to already disturbed ground on historical exploration grid lines. These results are from south of
the modelled Van Uden gold deposit and show that gold mineralisation continues beyond the
limit of modelling with similar widths and grades to the known deposit. Figure 1 shows the
location of the reported results for these drillholes.
Figure 2 shows a section through the middle of the new drilling in the area 550m south of the
Van Uden MRE. This area was ineffectively drilled historically with shallow drilling which failed
to reach the gold mineralised depth. A diamond drill core tail is planned for TGRC0128 to
intercept the footwall mineralisation and provide structural information to guide further drill
planning. The gold mineralisation occurs both at the meta sediments and basalt contact but is
stronger in the basalt footwall. Further drilling is required to test continuity of this mineralised
horizon. The full significant assay results above 0.3g/t Au are provided in Table 2.
ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
3
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Van Uden Exploration Drilling, continued
Figure 1 – Exploration Drilling Collars Showing Select Intercept Highlights (New Results in Yellow) and Pending Assay Drillholes
marked yellow collars and the Van Uden Gold Trend
ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
4
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Van Uden Exploration Drilling, continued
Figure 2 – Cross Section A-A’ Showing New Drilling, Historical Drilling and interpreted Mineralisation Envelope
The RC drilling for this report was conducted with a truck mounted Schramm T660 drill rig. A
total of 7 drillholes with assays returned and are included in this report for 678m of RC drilling.
The drillhole dips are all -60o which was deemed appropriate for first pass modern drilling in
this area. See Table 1 for drill collar information which includes new drilling results reported
here and pending drillholes still to be reported.
The reported drilling is in the far southern areas outside of the MRE. The drill collars of
drillholes with pending assays are also included in this report.
Individual 1m samples were taken where mineralisation was observed in the drillhole logging
and 4m composites taken outside of these zones. Both sample interval batches were assayed
using the Photon assay technique. Where the 4m composites recorded anomalous gold,
these samples were further analysed for the 1m split intervals. As experienced previously,
several drillholes recorded multiple gold mineralised intercepts downhole, refer to Table 2.
Hole TGGRC0127 recorded the best intercept and also multiple intercepts downhole, as
shown in the Figure 2 cross section. Mineralisation remains open down dip and along strike.
ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
5
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Table 1 – Drillhole Collar Information MGA2020, Zone 50
STATUS HOLE ID Dip(
o
) Azimuth(
o
) EASTING(m) NORTHING(m) RL (mASL) Depth (m)
Pending TGGR045 -60.000 250.000 750469.447 6439061.947 411.372 126
Pending TGGR046 -60.000 250.000 750518.297 6439080.946 410.539 168
Pending TGGR051 -60.000 250.000 750415.370 6439437.421 415.003 120
Pending TGGR052 -60.000 250.000 750402.321 6439484.348 415.248 132
Pending TGGR053 -60.000 250.000 750553.990 6439462.934 413.233 210
Pending TGGR054 -60.000 250.000 749612.913 6440448.136 435.244 126
Pending TGGR055 -60.000 250.000 749650.848 6440406.250 433.686 102
Pending TGGR056 -60.000 250.000 749692.166 6440367.628 432.995 102
Pending TGGR057 -60.000 250.000 749725.530 6440332.637 433.448 102
Pending TGGR058 -60.000 250.000 749794.539 6440300.222 432.615 108
Pending TGGR059 -60.000 250.000 749821.264 6440179.715 435.260 66
Pending TGGR060 -60.000 250.000 750125.925 6439889.536 425.652 120
Pending TGGR061 -90.000 0.000 750310.382 6439451.828 417.213 60
Pending TGGR088 -60.000 250.000 750353.249 6439207.772 414.695 60
Pending TGGR089 -60.000 250.000 750375.708 6439216.460 413.937 60
Pending TGGR090 -60.000 250.000 750312.073 6439204.298 416.087 54
Pending TGGR091 -60.000 250.000 749957.023 6439937.504 427.572 42
Pending TGGR092 -90.000 360.000 749917.769 6439947.798 428.074 30
Pending TGGR093 -90.000 360.000 749900.434 6439966.717 428.682 24
Pending TGGR094 -60.000 250.000 749566.266 6440274.014 430.907 24
Pending TGGR095 -60.000 250.000 749590.676 6440283.939 431.515 36
Pending TGGR096 -60.000 250.000 749776.590 6440137.459 434.463 30
Pending TGGR097 -60.000 250.000 749804.013 6440148.704 435.448 42
Pending TGGR098 -60.000 250.000 749828.479 6440159.131 435.454 60
Pending TGGR099 -60.000 250.000 750002.449 6439797.348 429.606 36
Pending TGGR100 -90.000 0.000 749462.385 6440374.657 438.340 42
Pending TGGR101 -90.000 0.000 749492.548 6440355.748 435.575 30
Pending TGGR102 -90.000 0.000 749501.308 6440327.814 434.144 24
Pending TGGR103 -90.000 0.000 749470.253 6440321.887 434.067 24
Pending TGGR104 -90.000 0.000 749378.783 6440343.497 438.410 24
Pending TGGR105 -90.000 0.000 749404.403 6440320.657 435.455 24
Pending TGGR106 -90.000 0.000 749352.911 6440308.636 435.877 24
Pending TGGR107 -90.000 0.000 749336.255 6440326.240 437.502 30
Pending TGGR108 -90.000 0.000 749235.198 6440362.974 438.071 54
Pending TGGR109 -90.000 0.000 749314.257 6440396.404 444.364 42
Pending TGGR110 -90.000 0.000 749278.412 6440385.805 442.107 30
Pending TGGR111 -60.000 250.000 749296.970 6440442.649 449.137 60
ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
6
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Table 1 – Drillhole Collar Information – Continued
STATUS HOLE ID Dip(o
) Azimuth(o
) EASTING(m) NORTHING(m) RL (mASL) Depth (m)
Pending TGGR112 -90.000 0.000 749260.613 6440482.813 452.538 72
Pending TGGR113 -60.000 250.000 749079.177 6440498.243 444.568 30
Pending TGGR114 -60.000 250.000 749074.641 6440522.319 446.389 48
Pending TGGR115 -60.000 250.000 749120.673 6440590.048 453.220 54
Pending TGGR116 -60.000 250.000 750441.212 6439131.432 412.065 102
Pending TGGR117 -60.000 250.000 750485.966 6439147.319 411.187 126
Pending TGGR118 -60.000 250.000 750529.957 6439161.407 410.500 168
Pending TGGRD119 -60.000 250.000 750582.698 6439173.767 409.897 203
Pending TGGR120 -60.000 250.000 750405.169 6439227.989 412.968 78
Pending TGGR121 -60.000 250.000 750453.284 6439246.413 411.800 126
Pending TGGR122 -60.000 250.000 750429.819 6439239.493 412.260 96
Pending TGGR123 -60.000 250.000 750439.130 6439209.067 412.156 108
NEW TGGR124 -60.000 250.000 750484.701 6438586.636 405.880 102
NEW TGGR125 -60.000 250.000 750579.049 6438616.152 405.804 96
NEW TGGR126 -60.000 250.000 750428.264 6438245.312 411.955 90
NEW TGGR127 -60.000 250.000 750496.823 6438269.164 409.462 78
NEW TGGR128 -60.000 250.000 750541.055 6438286.930 407.766 72
NEW TGGR129 -60.000 250.000 750642.165 6438321.776 404.648 120
NEW TGGR130 -60.000 250.000 750611.605 6437993.853 403.050 120
Pending TGGR131 -60.000 250.000 750100.836 6439723.308 429.255 54
Pending TGGR132 -60.000 250.000 749981.935 6440039.320 428.052 90
Pending TGGR133 -60.000 250.000 749964.261 6440072.227 429.372 90
Pending TGGR134 -60.000 250.000 749336.513 6440509.885 453.901 102
Pending TGGR135 -60.000 250.000 749379.558 6440523.461 451.140 90
Pending TGGR136 -60.000 250.000 749454.535 6440551.335 446.154 132
Pending TGGR137 -60.000 250.000 749192.238 6440567.877 456.990 96
Pending TGGR138 -60.000 250.000 749292.267 6440599.244 455.656 120
Pending TGGR139 -60.000 250.000 749393.635 6440636.418 449.274 156
Pending TGGR140 -60.000 250.000 750288.172 6439500.411 417.280 72
Pending TGGR141 -60.000 250.000 750316.895 6439509.850 416.921 72
Pending TGGR142 -60.000 250.000 750339.612 6439517.359 416.548 90
Pending TGGR143 -60.000 250.000 750367.025 6439526.805 416.047 114
Pending TGGR144 -60.000 250.000 750392.480 6439535.782 415.630 132
Pending TGGR145 -60.000 250.000 750469.206 6439216.147 411.446 132
Pending TGGR146 -60.000 250.000 750755.396 6435694.220 412.474 108
Pending TGGR147 -60.000 250.000 750943.785 6435760.318 414.651 102
Pending TGGR148 -60.000 250.000 750630.673 6437152.267 406.142 120
Pending TGGR149 -60.000 250.000 750727.698 6437182.860 405.691 96
Pending TGGR150 -60.000 250.000 749175.282 6440611.233 456.963 78
Pending TGGR151 -90.000 0.000 749303.379 6440289.614 434.042 18
Pending TGGR152 -60.000 250.000 749325.500 6440454.078 449.761 66
Pending TGGR156 -60.000 250.000 749843.987 6440132.286 435.775 48
Pending TGGR157 -60.000 250.000 749867.386 6440039.507 432.149 42
Pending TGGR158 -60.000 250.000 749910.985 6440056.644 431.379 66
Pending TGGR159 -60.000 250.000 749861.282 6440140.798 435.612 60
Pending TGGR160 -60.000 250.000 749874.401 6440147.005 434.902 72
ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
7
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Follow-up Work
Planning and preparation for first diamond drill core drilling is well advanced for
commencement in January 2026 which will include a diamond core tail on drillhole
TGGRC0128.
Ongoing drilling results will be used to update the current resource model, MRE (Table A) and
in addition four holes are outstanding in the far south exploration target positions.
Mineralisation and geology interpolation is ongoing as logging and assay data becomes
available.
Pending assays will be reported as they come to hand in January 2026.
Further drilling at the Gold City prospect will commence when approvals have been granted.
Soil sampling assays for Cronin West exploration tenement, Van Uden far north (Powerline
Prospecting Licence) and Gold City infill are also expected to return from the laboratory in the
coming weeks.
ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
8
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Van Uden Gold Project Description
The Project is located on the Forrestania Greenstone Belt, Figure 3, 90km east-northeast of
Hyden and 120km south of Southern Cross. It is close to the Marvel Loch (producing) and
Westonia - Edna May (care & maintenance) gold processing Plants. The Project lies 12.5km
to the south west of the Mt Holland lithium mine and is 130km north west from the Company’s
established Burmeister lithium deposit at the Lake Johnston Project.
Van Uden Gold consists of an Indicated and Inferred Mineral Resource as per Table A below
on four granted mining leases, four granted exploration licences, one exploration licence
application and two miscellaneous licences (for haul roads).
Table A: MRE – Van Uden Gold Deposit
The Mineral Resources statement conforms to the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (JORC Code) 2012 Edition. All tonnages are dry metric tonnes. It has been reported
at a cut-off grade of 0.35 g/t Au by area within a A$5,000/oz Au optimised pit shell based on mining parameters
and operating costs typical for Australian open pit extraction deposits of a similar scale and geology. Minor
discrepancies may occur due to rounding of appropriate significant figures.
The resources comply with the Reasonable Prospects for Eventual Economic Extraction (RPEEE), a key principle
in mineral resource reporting that requires the qualified person to demonstrate that a mineral deposit has the
potential to be economically extracted in the future.
About TG Metals
TG Metals is an ASX listed company focused on exploring and developing gold and lithium
assets at its wholly owned Lake Johnston Project and 80% owned Van Uden Gold Project in
the stable jurisdiction of Western Australia, Figure 4. The Lake Johnston Project hosts the
Burmeister high grade lithium deposit, Jaegermeister lithium pegmatites and several
surrounding lithium prospects. Burmeister is in proximity to four lithium processing plants and
undeveloped deposits. The Van Uden Gold Project contains past producing gold mines and
is in proximity to operating gold processing Plants.
Authorised for release by TG Metals Board of Directors.
Contact Investor Relations
Mr David Selfe Evy Litopoulous
Chief Executive Officer ResolveIR
Email: info@tgmetals.com.au Email: evy@resolveir.com
Material
Tonnes
Grade
(Aug/t) Gold (Oz) Tonnes
Grade
(Aug/t) Gold (Oz) Tonnes
Grade
(Aug/t) Gold (Oz)
Laterite 234,000 0.9 6,940 525,000 0.7 11,800 759,000 0.7 18,740
Oxide 867,000 1.2 34,200 1,141,000 1.0 38,200 2,008,000 1.0 72,400
Transitional 291,000 1.1 10,700 770,000 1.1 26,500 1,061,000 1.1 37,200
Fresh 318,000 1.6 16,500 2,207,000 1.2 82,300 2,525,000 1.2 98,800
Total 1,710,000 1.2 68,340 4,643,000 1.2 158,800 6,353,000 1.1 227,140
Mineral Resource Estimate for the VanUdenGold Deposit - May 2025
Indicated Inferred Total
ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
9
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Figure 3 – Location Map showing TG Metals’ Van Uden Gold Project
ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
10
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Figure 4 – Location Map showing TG Metals’ Lake Johnston Lithium and Van Uden Gold Projects
11
ASX ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Competent Person Statement
Information in this announcement that relates to exploration results, exploration strategy, exploration
targets, geology, drilling and mineralisation is based on information compiled by Mr David Selfe who is a
Fellow of the Australasian Institute of Mining and Metallurgy and an employee of TG Metals Limited. Mr
Selfe has sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activities that he is undertaking to qualify as a Competent Person as defined in
the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves. Mr Selfe has consented to the inclusion in this report of matters based on their information
in the form and context in which it appears. Mr Selfe considers that the information in this announcement
is an accurate representation of the available data and studies for the Van Uden Gold Project.
Forward Looking Statements
This announcement may contain certain statements that may constitute “forward looking statements”.
Such statements are only predictions and are subject to inherent risks and uncertainties, which could
cause actual values, results, performance achievements to differ materially from those expressed,
implied or projected in any forward looking statements.
Forward-looking statements are statements that are not historical facts. Words such as “expect(s)”,
“feel(s)”, “believe(s)”, “will”, “may”, “anticipate(s)” and similar expressions are intended to identify forward-
looking statements. These statements include, but are not limited to statements regarding future
production, resources or reserves and exploration results. All such statements are subject to certain risks
and uncertainties, many of which are difficult to predict and generally beyond the control of the Company,
that could cause actual results to differ materially from those expressed in, or implied or projected by,
the forward-looking information and statements. These risks and uncertainties include, but are not limited
to: (i) those relating to the interpretation of drill results, the geology, grade and continuity of mineral
deposits and conclusions of economic evaluations, (ii) risks relating to possible variations in reserves,
grade, planned mining dilution and ore loss, or recovery rates and changes in project parameters as
plans continue to be refined, (iii) the potential for delays in exploration or development activities or the
completion of feasibility studies, (iv) risks related to commodity price and foreign exchange rate
fluctuations, (v) risks related to failure to obtain adequate financing on a timely basis and on acceptable
terms or delays in obtaining governmental approvals or in the completion of development or construction
activities, and (vi) other risks and uncertainties related to the Company’s prospects, properties and
business strategy. Our audience is cautioned not to place undue reliance on these forward-looking
statements that speak only as of the date hereof, and we do not undertake any obligation to revise and
disseminate forward-looking statements to reflect events or circumstances after the date hereof, or to
reflect the occurrence of or non-occurrence of any events.
The Company believes that it has a reasonable basis for making the forward-looking Statements in the
presentation based on the information contained in this and previous ASX announcements.
The Company is not aware of any new information or data that materially affects the information included
in this ASX release, and the Company confirms that, to the best of its knowledge, all material assumptions
and technical parameters underpinning the exploration results in this release continue to apply and have
not materially changed.
12
ASX ASX ANNOUNCEMENT I RELEASED 20 JANUARY 2026
________________________________________________________________
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Table 2 – Drill Assay Table – NSI=no significant Intercept (<0.3g/tAu), All 1m intervals
Hole ID FROM To PROSPECT Au (g/t)
TGGR124 0 26 VU South Ext NSI
TGGR124 26 27 VU South Ext 0.48
TGGR124 27 71 VU South Ext NSI
TGGR124 71 72 VU South Ext 9.83
TGGR124 72 73 VU South Ext 0.21
TGGR124 73 74 VU South Ext 0.34
TGGR124 74 100 VU South Ext NSI
TGGR125 0 32 VU South Ext NSI
TGGR125 32 33 VU South Ext 0.37
TGGR125 33 34 VU South Ext 0.56
TGGR125 34 96 VU South Ext NSI
TGGR126 0 52 VU South Ext NSI
TGGR126 52 56 VU South Ext 0.19
TGGR126 56 90 VU South Ext NSI
TGGR127 0 35 VU South Ext NSI
TGGR127 35 36 VU South Ext 0.34
TGGR127 36 37 VU South Ext 0.33
TGGR127 37 38 VU South Ext 0.25
TGGR127 38 39 VU South Ext 0.32
TGGR127 39 40 VU South Ext 0.33
TGGR127 40 41 VU South Ext 0.21
TGGR127 41 42 VU South Ext 0.1
TGGR127 42 43 VU South Ext 0.24
TGGR127 43 44 VU South Ext 0.18
TGGR127 44 45 VU South Ext 0.51
TGGR127 45 46 VU South Ext 1.2
TGGR127 46 47 VU South Ext 1.0
TGGR127 47 48 VU South Ext 0.25
TGGR127 48 49 VU South Ext 0.11
TGGR127 49 50 VU South Ext <0.03
TGGR127 50 51 VU South Ext 0.26
TGGR127 51 52 VU South Ext 0.38
TGGR127 52 53 VU South Ext 0.2
TGGR127 53 61 VU South Ext NSI
TGGR127 61 62 VU South Ext 0.55
TGGR127 62 63 VU South Ext 0.17
TGGR127 63 64 VU South Ext 0.07
TGGR127 64 65 VU South Ext 0.15
TGGR127 65 66 VU South Ext 6.18
TGGR127 66 67 VU South Ext 0.26
TGGR127 67 68 VU South Ext 0.38
TGGR127 68 69 VU South Ext 0.06
TGGR127 69 70 VU South Ext 0.05
TGGR127 70 71 VU South Ext 1.56
TGGR127 71 72 VU South Ext 0.91
TGGR127 72 73 VU South Ext 0.55
TGGR127 73 74 VU South Ext 0.97
TGGR127 74 75 VU South Ext 9.66
TGGR127 75 76 VU South Ext 0.38
TGGR127 76 77 VU South Ext 0.09
TGGR127 77 78 VU South Ext 0.05
TGGR128 0 32 VU South Ext NSI
TGGR128 32 36 VU South Ext 0.24
TGGR128 32 33 VU South Ext <0.03
TGGR128 33 34 VU South Ext 0.30
TGGR128 34 35 VU South Ext 0.28
TGGR128 35 36 VU South Ext 0.2
TGGR128 36 72 VU South Ext NSI
TGGR129 0 80 VU South Ext NSI
TGGR129 80 81 VU South Ext 0.23
TGGR129 81 82 VU South Ext 0.32
TGGR129 82 83 VU South Ext 0.15
TGGR129 83 84 VU South Ext 0.24
TGGR129 84 120 VU South Ext NSI
TGGR130 0 120 VU South Ext NSI
1
JORC Code, 2012 Edition – Table 1
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling (eg cut channels, random chips, or
specific specialised industry standard measurement tools appropriate
to the minerals under investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity
and the appropriate calibration of any measurement tools or systems
used.
• Aspects of the determination of mineralisation that are Material to the
Public Report.
• In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1
m samples from which 3 kg was pulverised to produce a 30 g charge
for fire assay’). In other cases more explanation may be required,
such as where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types (eg
submarine nodules) may warrant disclosure of detailed information.
• All holes were sampled at 1 m intervals using an on-board Ox
Cyclone Sampling system with fixed cone splitter engineered for
the rig. Samples outside of the known gold mineralised zones are
composited to 4m samples and assayed prior to the 1m intervals
being submitted for assay. 4m composite samples are not reported.
• Two samples (Original + Duplicate) were collected each metre,
representing 12.5 % of total cyclone discharge per split.
• Certified reference materials (CRMs) were inserted every 20
samples, and coarse blanks every 40 samples. All samples were
dry.
• Samples were transported to Laboratory: SGS Australia Pty Ltd,
Kalgoorlie WA (17 Stockyard Way) for PhotonAssay™ PAAU02,
two-cycle analysis on 500g of crushed material.
Drilling
techniques
• Drill type (eg core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple
or standard tube, depth of diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by what method, etc).
• Reverse-circulation (RC) drilling Drilling was completed using three
rigs, selected to match depth requirements and operational
efficiency
• Impact Drilling – RIG 02
o Rig: Schramm T660 (8×8 MAN carrier)
o Year: 2006 (rebuilt 2021)
o Capability: High-capacity deep RC drilling
o Depth capacity: >500 m (4.5″ RC)
o Rod handling: KL rod handler
• Safety & control: KL rod handler, TJM hands-free breakout, rear-
mounted controls, onboard dust collection and suppression.
Drill sample
recovery
• Method of recording and assessing core and chip sample recoveries
and results assessed.
• Measures taken to maximise sample recovery and ensure
• Sample recovery was visually assessed and recorded by comparing
the two splitter outputs each metre.
• All samples were dry with negligible loss.
2
Criteria JORC Code explanation Commentary
representative nature of the samples.
• Whether a relationship exists between sample recovery and grade
and whether sample bias may have occurred due to preferential
loss/gain of fine/coarse material.
• Given the dry conditions and fixed splitter configuration, no material
bias is expected.
Logging • Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.
•
• Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.
• The total length and percentage of the relevant intersections logged.
• RC drill cuttings of the metre intervals were sieved, washed and
placed into a chip tray for geological logging and for future
reference. Clay intervals in regolith were not sieved, however any
remnant rock/hard material were sieved and washed for
identification.
• TG Metals Limited geological logging system:
o Recognises fresh rock vs regolith.
o Is both qualitative and quantitative.
o Industry and geological standards were followed recording
every detail observed.
o Every interval (m) drilled was logged.
o 20m interval Chip trays were labelled and used to store a
small representative sample for future reference.
Sub-sampling
techniques
and sample
preparation
• If core, whether cut or sawn and whether quarter, half or all core
taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.
• For all sample types, the nature, quality and appropriateness of the
sample preparation technique.
• Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
• Measures taken to ensure that the sampling is representative of the in
situ material collected, including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of the material
being sampled.
• Samples were split at the rig using a fixed cone splitter, producing
two by