Positive Metallurgical Testwork Results
for Van Uden Stockpiles
Highlights
TG Metals Limited (TG Metals or the Company) (ASX:TG6) is pleased to provide final results
from metallurgical testwork on the mineralised stockpiles at the Van Uden Gold Project in
Western Australia.
TG Metals CEO, Mr. David Selfe stated;
“This testwork confirms the positive metallurgical characteristics of the stockpile ore to be
treated at a standard Carbon in Leach (CIL) Processing Plant.
The full metallurgical report and testwork data will be provided to potential third party treatment
facilities in the region with a view to securing a treatment pathway for the stockpiles and
potentially the larger Van Uden resources.
The metallurgical testwork will also be used to compliment future feasibility studies for the
wider Van Uden Gold Project.”
Gold Testwork Overview
TG Metals engaged Independent Metallurgical Operations Pty Ltd (IMO) based in Western
Australia, to conduct metallurgical testwork on sonic core samples recovered from previous
mining stockpiles at the Company’s Van Uden Gold project. Testwork was completed at
Metallurgy Pty Ltd, a commercial laboratory located in Perth WA. The results and testwork
program were overseen by independent consultant Michael Rodriguez, who has over 35 years
of practical and technical experience in the mining, minerals processing, hydrometallurgical
and pyrometallurgical industries.
This testwork was primarily to determine the amenability of the ore to conventional gravity
concentration and cyanide leaching, in preparation for TG Metal’s intended toll-treatment
pathway for the Van Uden stockpiles.
■ Metallurgical testwork on composite samples taken from the gold
mineralised stockpiles delivers excellent results with recoveries up to
90.7% gold achieved
■ Consistent uplift in calculated head grade of the composite samples v’s
assayed head grade indicating coarse gold
■ Testwork shows soft to medium material crushing and grinding
characteristics for majority of stockpile
■ Leaching tests show low lime consumption
■ Very positive results to underpin future engineering studies and
confirmatory testwork
ASX ANNOUNCEMENT I RELEASED 2 OCTOBER 2025
________________________________________________________________
2
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
A total of four (4) composites were generated utilising the sonic drill core intervals provided
from the Company’s drilling campaign. These intervals first underwent individual preparation
to facilitate interval gold assay and selected intervals were used to form the composites. Each
composite represents one of the historic stockpiles at Van Uden, namely the Tasman Mafics
(TM), Tasman Sediments (TS), Dieman Laterite (DL) and Dieman Oxide (DO). Additional grab
samples for each of the stockpiles was also obtained to form six (6) comminution samples for
Bond Ball Index testing.
The key findings from this testwork can be summarised as follows:
• Composite assay gold head grades ranging from 0.66 g/t to 0.95 g/t;
• Overall gold recoveries ranging from 88.5% to 90.7%, with gravity gold recoveries ranging
from 13.0% to 22.5%;
• Leaching appears to be completed after 24 hours for all composites, see Figure 1;
• Bond Ball Work Index Testing highlighted the following:
o TS stockpile was classified as medium to hard;
o TM stockpile was classified as soft to medium hardness;
o DO and DT stockpiles were both classified as very hard.
Table 1 – Overall Gravity/Leach Results Summary
Composite
Composite
TM
Composite
TS
Composite
DL
Composite
DO
Leach Test # LT01 LT02 LT03 LT04
Calculated Ore Head Grade g/t 1.27 1.05 0.99 0.81
Assay Ore Head Grade g/t 0.66 0.95 0.80 0.71
Gravity Recovery % 22.5% 13.0% 15.0% 19.9%
2 Hour Overall Recovery % 44.8% 42.8% 57.2% 55.0%
4 Hour Overall Recovery % 53.4% 61.9% 63.2% 61.4%
8 Hour Overall Recovery % 64.3% 81.7% 72.9% 76.9%
24 Hour Overall Recovery % 87.8% 86.9% 87.5% 90.5%
48 Hour Overall Recovery % 89.3% 88.5% 89.4% 90.7%
Leach Residue Grade g/t 0.14 0.12 0.11 0.08
Gravity Gold Recovery g/t 0.28 0.14 0.15 0.16
Leach Gold Recovery g/t 0.85 0.79 0.73 0.57
Overall Gold Recovery g/t 1.13 0.93 0.88 0.73
Total NaCN Cons kg/t 0.78 0.74 0.71 0.56
Total Lime Cons kg/t 0.25 0.72 0.55 0.00
ASX ANNOUNCEMENT I RELEASED 2 OCTOBER 2025
________________________________________________________________
3
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
IMO notes that improved recoveries and leach kinetics may be obtained with reduced grind
size and reagent optimisation. However, IMO recommends that further optimisation work be
conducted after the selection of a toll-treatment plant and specification of plant capability.
Figure 1 - Leaching Times for all 4 Leach Tests
To avoid any bias, sample intervals were selected by IMO to form composites representing
the TM, TS, DL and DO stockpiles as shown in Appendix 1, Figure 2 to Figure 4. The details
of each composite can be found in Appendix 1, Table 2.
The Bond Ball Work Index testing arrived at the following results which indicate a mix of
material types from Soft to Very Hard. The softest material is the Mafic Stockpile whilst the
hardest is the Dieman Laterite stockpile, both of which are unsurprising.
Grab-samples from each stockpile underwent Bond Ball Work Index testing at a closing
screen size of 106μm. The results, indicate the following:
• The TS stockpile reported BBWis of 12.1 and 15.6 kWh/t, classifying the material as
medium to hard;
• The TM stockpile reported BBWis of 7.8 and 9.4 kWh/t, classifying the material as soft to
medium hardness;
• The DO and DL stockpiles reported BBWis of 20.2 and 21.9 kWh/t respectively,
classifying both material types as very hard likely due to the Pisolite and Quartz content.
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
0 4 8 12 16 20 24 28 32 36 40 44 48
Overall
Gold
Recovery
(%)
Leach Time (hrs)
LT01 LT02 LT03 LT04
ASX ANNOUNCEMENT I RELEASED 2 OCTOBER 2025
________________________________________________________________
4
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
APPENDIX 1 – Composite Sample Locations and Intervals
Figure 2 – Mafic Stockpile (TM) Composite Drillhole Selection
ASX ANNOUNCEMENT I RELEASED 2 OCTOBER 2025
________________________________________________________________
5
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Figure 3 – Sediments Stockpile (TS) Composite Drillhole Selection
Figure 4 – Dieman Oxide (DO) and Laterite Stockpile (DL) Composite Drillhole Selection
ASX ANNOUNCEMENT I RELEASED 2 OCTOBER 2025
________________________________________________________________
6
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Table 2 – Composites taken from Sonic drill core
Composite Hole ID From To
Interval
Mass
Interval
Au Grade
Composite
Mass
Composite
Au Grade
m m kg g/t kg g/t
TM
HGTS03 0 4.00 15.6 0.63
141.0 0.95
HGTS05 0 4.50 18.7 1.27
HGTS07 0 3.90 15.6 1.03
HGTS10 0 4.50 17.9 1.43
HGTS12 0 3.40 11.6 0.72
HGTS16 0 2.60 13.1 0.88
HGTS19 0 4.50 27.6 1.13
HGTS21 0 4.75 20.9 0.34
TS
LGVU02 0 3.70 18.3 1.24
153.5 0.84
LGVU08 0 3.79 24.6 0.82
LGVU17 0 4.42 24.7 0.77
LGVU19 0 4.95 14.1 1.59
LGVU23 0 4.85 26.3 0.53
LGVU30 0 3.70 17.3 0.80
LGVU38 0 2.40 8.3 0.88
LGVU42 0 4.40 19.9 0.43
DL
LT01 0 1.80 11.9 0.62
115.3 0.80
LT04 0 1.40 9.7 0.79
LT09 0 1.40 9.3 0.63
LT13 0 0.90 8.9 1.07
LT19 0 2.70 18.4 1.03
LT28 0 2.40 22.1 0.64
LT33 0 2.70 15.7 0.81
LT35 0 2.10 19.3 0.83
DO
OX05 0 0.80 4.2 0.70
85.8 0.70
OX17 0 1.00 3.4 1.57
OX20 0 1.20 6.9 0.49
OX26 0 2.40 10.5 0.65
OX29 0 2.80 13.6 0.85
OX31 0 2.70 13.7 0.61
OX33 0 2.40 16.3 0.47
OX37 0 2.90 17.2 0.83
Full stockpile drilling results previously reported 21 August 2025.
ASX ANNOUNCEMENT I RELEASED 2 OCTOBER 2025
________________________________________________________________
7
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Table 3 – Collar Surveys of Metallurgical Sample Drillholes
Hole ID
Total
Depth
Easting Easting RL Dip
Tenement
No.
HGTS03 4.0 750186 6439425 424.3 -90 M77/478
HGTS05 5.0 750175 6439446 424.4 -90 M77/478
HGTS07 5.0 750158 6439448 424.1 -90 M77/478
HGTS10 5.0 750149 6439430 424.6 -90 M77/478
HGTS12 4.0 750158 6439411 424.2 -90 M77/478
HGTS16 3.0 750177 6439405 424.5 -90 M77/478
HGTS19 5.0 750168 6439426 424.5 -90 M77/478
HGTS20 5.0 750172 6439435 424.7 -90 M77/478
HGTS21 5.0 750162 6439436 424.6 -90 M77/478
LGVU02 3.8 750072 6439347 427.4 -90 M77/478
LGVU08 4.0 750047 6439341 428.2 -90 M77/478
LGVU17 4.5 750052 6439331 428.3 -90 M77/478
LGVU19 5.5 750081 6439328 427.6 -90 M77/478
LGVU23 5.0 750067 6439319 427.8 -90 M77/478
LGVU24 5.0 750056 6439319 428.3 -90 M77/478
LGVU30 4.0 750013 6439314 428.5 -90 M77/478
LGVU38 4.0 750036 6439302 428.2 -90 M77/478
LGVU42 5.0 750022 6439331 428.5 -90 M77/478
LT01 2.0 749462 6440092 426.4 -90 M77/477
LT04 2.0 749487 6440092 427.0 -90 M77/477
LT09 1.5 749514 6440071 425.9 -90 M77/477
LT13 1.0 749504 6440048 425.5 -90 M77/477
LT19 2.9 749480 6440026 423.8 -90 M77/477
LT28 3.0 749498 6440081 427.5 -90 M77/477
LT33 2.8 749466 6440073 427.2 -90 M77/477
LT35 2.2 749480 6440065 426.9 -90 M77/477
OX05 1.0 749408 6440055 424.0 -90 M77/477
OX17 1.0 749436 6440058 424.9 -90 M77/477
OX20 1.7 749424 6440067 425.3 -90 M77/477
OX26 2.6 749434 6440077 426.7 -90 M77/477
OX29 3.0 749421 6440087 427.0 -90 M77/477
OX31 2.8 749442 6440087 427.2 -90 M77/477
OX33 2.5 749441 6440034 423.6 -90 M77/477
OX37 3.0 749414 6440035 423.4 -90 M77/477
8
ASX ASX ANNOUNCEMENT I RELEASED 2 OCTOBER 2025
________________________________________________________________
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Next Steps
The full metallurgical report will be made available to potential third party treatment suppliers
in the region in continued discussions on toll treatment/ore purchase opportunities.
Further optimisation testwork is planned to achieve improved overall gold recoveries as
recommended by IMO.
Drilling continues at pace on the Van Uden resource expansion, Tasman in-pit and at Gold
City exploration. Results from these three key drilling areas are expected to start returning
later in October.
Site works continue in preparation for further drilling campaigns including diamond core drilling
and for haulage of stockpiles offsite once a suitable treatment agreement is executed.
9
ASX ASX ANNOUNCEMENT I RELEASED 2 OCTOBER 2025
________________________________________________________________
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
About TG Metals
TG Metals is an ASX listed company focused on exploring and developing gold and lithium
assets at its wholly owned Lake Johnston Project and 80% owned Van Uden Gold Project in
the stable jurisdiction of Western Australia. The Lake Johnston Project hosts the Burmeister
high grade lithium deposit, Jaegermeister lithium pegmatites and several surrounding lithium
prospects. Burmeister is in proximity to four lithium processing plants and undeveloped
deposits. The Van Uden Gold Project contains past producing gold mines and is in proximity
to operating gold processing Plants, see Figure 5 below.
Authorised for release by TG Metals Board of Directors.
Contact Investor Relations
Mr David Selfe Evy Litopoulous
Chief Executive Officer ResolveIR
Email: info@tgmetals.com.au Email: evy@resolveir.com
Figure 5 – Location Map showing TG Metals’ Van Uden Gold Project
10
ASX ASX ANNOUNCEMENT I RELEASED 2 OCTOBER 2025
________________________________________________________________
TG METALS LTD
ASX TG6
ABN 40 644 621 830
Level 2, Suite 3
28 Ord Street
West Perth WA 6005
T: +61 8 6211 5099
W: www.tgmetals.com.au
Competent Person Statement
Information in this announcement that relates to exploration results, exploration strategy, exploration
targets, geology, drilling and mineralisation is based on information compiled by Mr David Selfe who is a
Fellow of the Australasian Institute of Mining and Metallurgy. Mr Selfe has sufficient experience that is
relevant to the style of mineralisation and type of deposit under consideration and to the activities that
he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Selfe has
consented to the inclusion in this report of matters based on their information in the form and context in
which it appears.
Information in this announcement that relates to metallurgical results, is based on information compiled
by Mr David Selfe and has been reviewed by Mr Michael Rodriguez who is a Fellow of the Australasian
Institute of Mining and Metallurgy. Mr Rodriguez has sufficient experience that is relevant to the style of
mineralisation and type of deposit under consideration and to the activities that he is undertaking to
qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of
Metallurgical Results. Mr Rodriguez has consented to the inclusion in this report of matters based on
their information in the form and context in which it appears.
Forward Looking Statements
This announcement may contain certain statements that may constitute “forward looking statements”.
Such statements are only predictions and are subject to inherent risks and uncertainties, which could
cause actual values, results, performance achievements to differ materially from those expressed,
implied or projected in any forward looking statements.
Forward-looking statements are statements that are not historical facts. Words such as “expect(s)”,
“feel(s)”, “believe(s)”, “will”, “may”, “anticipate(s)” and similar expressions are intended to identify forward-
looking statements. These statements include, but are not limited to statements regarding future
production, resources or reserves and exploration results. All such statements are subject to certain risks
and uncertainties, many of which are difficult to predict and generally beyond the control of the Company,
that could cause actual results to differ materially from those expressed in, or implied or projected by,
the forward-looking information and statements. These risks and uncertainties include, but are not limited
to: (i) those relating to the interpretation of drill results, the geology, grade and continuity of mineral
deposits and conclusions of economic evaluations, (ii) risks relating to possible variations in reserves,
grade, planned mining dilution and ore loss, or recovery rates and changes in project parameters as
plans continue to be refined, (iii) the potential for delays in exploration or development activities or the
completion of feasibility studies, (iv) risks related to commodity price and foreign exchange rate
fluctuations, (v) risks related to failure to obtain adequate financing on a timely basis and on acceptable
terms or delays in obtaining governmental approvals or in the completion of development or construction
activities, and (vi) other risks and uncertainties related to the Company’s prospects, properties and
business strategy. Our audience is cautioned not to place undue reliance on these forward-looking
statements that speak only as of the date hereof, and we do not undertake any obligation to revise and
disseminate forward-looking statements to reflect events or circumstances after the date hereof, or to
reflect the occurrence of or non-occurrence of any events.
The Company believes that it has a reasonable basis for making the forward-looking Statements in the
presentation based on the information contained in this and previous ASX announcements.
The Company is not aware of any new information or data that materially affects the information included
in this ASX release, and the Company confirms that, to the best of its knowledge, all material assumptions
and technical parameters underpinning the exploration results in this release continue to apply and have
not materially changed.
1
JORC Code, 2012 Edition – Table 1
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling (eg cut channels, random chips, or
specific specialised industry standard measurement tools appropriate
to the minerals under investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity
and the appropriate calibration of any measurement tools or systems
used.
• Aspects of the determination of mineralisation that are Material to the
Public Report.
• In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1
m samples from which 3 kg was pulverised to produce a 30 g charge
for fire assay’). In other cases more explanation may be required,
such as where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types (eg
submarine nodules) may warrant disclosure of detailed information.
• Sonic drilling was used to obtain continuous 4” diameter core from
surface stockpiles. Samples were collected into sealed plastic
sleeves to preserve in-situ moisture and laid into PQ trays. All
samples were transported to Independent Metallurgical Operations
(IMO) in Welshpool, Perth. Samples were weighed “as received,”
then dried and reweighed. Split sub-samples were created for
duplicate gold assay using 30g fire assay.
• Samples for Comminution* testwork were obtained from grab
samples of coarse material from each of the four stockpiles. The
technique used was random grab into 9 litre buckets from the sides
of the stockpiles and the tops of the stockpiles.
Metallurgical Testwork Sampling
• Sonic drill core was selected for inclusion in four composite
samples at Metallurgy Pty Ltd in Welshpool. All testwork was
managed by Independent Metallurgical Operations Pty Ltd (IMO).
• The four composites were domained by individual stockpile, being
the TM, TS, DO and DL stockpiles, all with different dominant
material types.
• Table 2 in the body text defines the components of the 4 composite
samples generated from the Sonic core across the four stockpiles.
Testwork Stages
Stage 1: Drill Interval Preparation & Analysis
o Inventory of Sonic Drill intervals
o Interval preparation and splitting for assay
o Moisture & Density analysis on selected intervals
o Duplicate gold interval assays
Stage 2: Gravity & Leach Testwork
o Generation of Composites
2
Criteria JORC Code explanation Commentary
o Comprehensive Head Assay
o Head Sizing Analysis
o Gravity Concentration & Intensive Leach
o Cyanide Leach Test
Additional Comminution Testwork
o Bond Ball Work Index on stockpile grab-samples*
This report details results from Stage 2 including the additional
Comminution testwork.
Gravity and Leach Testwork
Head Assay -
Sub-splits of the -2mm composites were pulverised and submitted to
SGS Australia Laboratory for the following analysis:
o Duplicate 50 g fire assay;
o Four acid digest – ICP/OES+MS;
o Carbon, Sulphur and Copper Speciation.
Size by Size Analysis -
Size by size assay analysis was undertaken on the 2mm crushed
material of each composite. The stage gold grades and cumulative gold
distributions for each composite were calculated. Gold distribution
generally follows the mass throughout the samples, indicating no
opportunity for scalp screening/pretreatment prior to leaching.
Gravity Concentration
Gravity recoverable gold analysis was undertaken on all four composites
prior to cyanide leach testing. a 15 kg sub split of the composites were
ground to 80% passing 300 μm and passed as a single pass through a
3” standard Knelson concentrator. The Knelson concentrate was
subsequently intensively leached, emulating industry standard gravity
concentrate leach conditions. Following gravity concentration, the
Knelson tails and intensive leach residues were recombined and split
into 1 kg charges for cyanide leaching.
3
Criteria JORC Code explanation Commentary
Cyanide Leach
The combined gravity tailings from each composite underwent a
conventional cyanide leach test, conducted at the following conditions:
• 1 kg solids;
• P80 106 μm;
• 40% solids in Perth tap water;
• 500 ppm NaCN initial, maintained at 300 ppm;
• Dissolved oxygen maintained between 8-10 mg/L by air addition;
• pH maintained at 9.5-10 with lime;
• Monitoring at 2, 4, 8, 24 and 48 hours.
Bond Ball Work Index
Separate from the composites discussed above, six (6) grab-samples
were taken from the Van Uden stockpiles, as shown in the Table below.
Each of these grab-samples underwent Bond Ball Work Index testing at
a closing screen size of 106μm.
Drilling
techniques
• Drill type (eg core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple
or standard tube, depth of diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by what method, etc).
• Sonic drilling was conducted using a GeoSonic EP26 66Hz rig with
4” tooling. All holes were vertical and drilled until base or near base
of stockpiles.
Drill sample
recovery
• Method of recording and assessing core and chip sample recoveries
and results assessed.
• Measures taken to maximise sample recovery and ensure
representative nature of the samples.
• Whether a relationship exists between sample recovery and grade
and whether sample bias may have occurred due to preferential
loss/gain of fine/coarse material.
• Considered very high due to sonic sampling performance. All
recovery was assessed through dry and as-received mass
comparison at IMO.
• Stock material has variations in compaction/settling as well as
being recently moved during earthworks to make the area suitable
for drilling.
4
Criteria JORC Code explanation Commentary
Logging • Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.
• Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.
• The total length and percentage of the relevant intersections logged.
• No formal geological logging was performed. Each hole was
categorised based on visual identification of stockpile material, soil,
or saprolite to identify the transition from dump to in-situ ground.
Sub-sampling
techniques
and sample
preparation
• If core, whether cut or sawn and whether quarter, half or all core
taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.
• For all sample types, the nature, quality and appropriateness of the
sample preparation technique.
• Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
• Measures taken to ensure that the sampling is representative of the in
situ material collected, including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of the material
being sampled.
• Samples were dried, weighed, and split at IMO to produce original
and duplicate sub-samples. Sonic run length dictated the sampling
interval, which was typically 1m where possible.
Quality of
assay data
and
laboratory
tests
• The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is considered
partial or total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc,
the parameters used in determining the analysis including instrument
make and model, reading times, calibrations factors applied and their
derivation, etc.
• Nature of quality control procedures adopted (eg standards, blanks,
duplicates, external laboratory checks) and whether acceptable levels
of accuracy (ie lack of bias) and precision have been established.
• All assays were conducted at SGS Laboratories using 30g Fire
Assay for gold. Duplicates were generated by physical splitting,
and both original and duplicate samples were analysed. No field
standards or blanks were inserted due to metallurgical scope and
internal QAQC at the lab.
Verification of
sampling and
assaying
• The verification of significant intersections by either independent or
alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.
• Discuss any adjustment to assay data.
• Sample data was verified by TG Metals personnel. LGVU42 was
drilled to replace LGVU13, which failed to penetrate sufficiently.
Variability between some intervals suggests a moderate nugget
effect, which has been mitigated through increased sampling
volume and mass-based averaging.
5
Criteria JORC Code explanation Commentary
Location of
data points
• Accuracy and quality of surveys used to locate drill holes (collar and
down-hole surveys), trenches, mine workings and other locations
used in Mineral Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• All collar positions were collected using handheld GPS. Stockpiles
are surface landforms, Post drilling a LiDAR survey was
undertaken allowing RL’s to be determined accurately.
Data spacing
and
distribution
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s) and
classifications applied.
• Whether sample compositing has been applied.
• Drilling was conducted in a 5–20m grid pattern across each dump.
464 sample intervals were generated. Mass-weighted averaging
was used to reduce bias caused by compaction variability.
Orientation of
data in
relation to
geological
structure
• Whether the orientation of sampling achieves unbiased sampling of
possible structures and the extent to which this is known, considering
the deposit type.
• If the relationship between the drilling orientation and the orientation
of key mineralised structures is considered to have introduced a
sampling bias, this should be assessed and reported if material.
• Not applicable. All stockpiles are anthropogenic with sub-horizontal
geometry. All holes were vertical.
Sample
security
• The measures taken to ensure sample security. • Samples were bagged, steel-strapped to pallets on-site, and
trucked directly to IMO in Welshpool. Chain of custody was
maintained by TG Metals personnel.
Audits or
reviews
• The results of any audits or reviews of sampling techniques and data. • No independent audits have been conducted at this stage. Results
and procedures are under internal review.
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status
• Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint
ventures, partnerships, overriding royalties, native title interests,
historical sites, wilderness or national park and environmental
settings.
• The security of the tenure held at the time of reporting along with any
• Tenements M77/478, M77/477 are located in Western Australia.
• Ownership: TG Metals acquiring 80% ownership of the Mining and
Exploration tenements from Montague Resources Australia Pty Ltd.
TG Metals acquiring 100% Ownership of Miscellaneous licences.
• The tenements are granted and in good standing.
6
Criteria JORC Code explanation Commentary
known impediments to obtaining a licence to operate in the area.
Exploration
done by other
parties
• Acknowledgment and appraisal of exploration by other parties. • Historical exploration by Reynolds Australia, PacMin Mining
Corporation, Convergent Minerals, Viceroy Australia Pty Ltd,
Forrestania Gold NL, Sons of Gwalia Limited, St Barbara Mines
Limited, Montague Resources Australia Pty Ltd, Kidman Resources
Limited, Tianye SXO Gold Mining Pty Ltd, and MH Gold Ltd.
• Data has been obtained from WAMEX Open File reports.
Geology • Deposit type, geological setting and style of mineralisation. • Hosted within the Southern Cross Greenstone Belt.
• Gold mineralisation is structurally controlled, occurring along shear
zones and in quartz veins.
• The geological structure had previously been interpreted as a
shallowly eastward dipping system associated with a generally NNW
striking contact zone.
• Previously mined material concentrated on Oxide and Lateritic ore.
Drill hole
Information
• A summary of all information material to the understanding of the
exploration results including a tabulation of the following information
for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in
metres) of the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
• If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from
the understanding of
Share your feedback
Discover